• Design stage – One-stage. Design in the stage of Working Project;
  • Section length – 12.4 km;
  • Road category – ІІ;
  • Object belongs to the CC3 consequence class;
  • Engineering surveys: topographic-geodesic; engineering-geological;
  • Installation of pipe culverts and bus stops;
  • Arrangement of a platform for the location of dimensional and weight control point;
  • Installation of road signs and road markings with high reflectivity;
  • Installation of lighting at intersections, places with speed change lanes and in all places of concentration of road accidents;
  • Project expertise and obtention of a positive expert report.